摘要:对于【信息系统项目管理师】软考考试而言,试题无疑是最重要的学习资料之一。在软考备考过程中,吃透所考知识点、熟悉出题思路,对我们提升分数的效果是最明显的,通过试题反复练习,还可以查漏补缺。今天,给大家带来【信息系统项目管理师】部分试题的详解,一起来看看吧~



1、estimating schedule activity costs involves developing an () of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives.for example,in mostapplication areas,additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product oprations.the cost estimating process considers whether the expected savings can offset the cost of the additional design work.cost estmates are generally expressed in units of () to facilitate comparisons both within and across projects.the (请作答此空) describes important information about prject requirement that is considered duing cost estimating.
A、 project scope statement
B、 statement of work
C、 project management plan
D、 project policy

答案:A
答题解析:

估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本,成本估算包括设别和考虑各种成本计算方案。例如:在多数的应用领域,普遍在设计阶段多做些额外工作以降低在执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般是以货币单位表示,以利于在项目内和项目间进行比较,项目范围说明书描述了项目的商业要求、理由、需求和当前边界,它提供了关于在成本估算时必须考虑的项目需求的重要信息。



2、在项目管理当中,下列关于“间接管理”的论述中正确的是“间接管理”() 。
A、 有利于信息传递
B、 不利于解决管理幅度问题
C、 依赖于管理制度的建设
D、 更容易建立管理者和被管理者之间的沟通和信任

答案:C
答题解析:间接管理是指组织的最终责任不直接对组织内的每个人和每件事进行管理,而是通过授权和建立工作机制来对组织进行管理。这样就存在不同层面的管理层,可能会导致组织在信息传递上出现问题,不同层面、不同部分的管理者和被管理者之间也难以构建起信任,同时其必须依靠一套规范的制度来维持。

3、战略管理的主要活动可以分为下列中的()
A、 战略分析、战略执行、战略评估
B、 战略制定、战略执行、战略评估
C、 战略分析、战略制定、战略执行
D、 战略分析、战略制定、战略评估

答案:B
答题解析:

企业是一个复杂动态开放的系统,有效的项目管理活动必须能根据企业战略要求,并从企业整体角度出发整合其范围内的所有项目管理活动,进行企业战略管理,将分散于企业系统中的项目管理活动集成到战略范畴。
战略管理是指对一个组织的未来方向制定决策和实施这些决策,它大体可以分解如下。
(1)战略制定:企业制定战略的步骤包括明确企业使命、进行外部环境分析、展开内部环境评估、确定战略目标、形成战略方案,以及选择战略方案。
(2)战略执行:企业的战略一旦形成后,战略管理的关键就是战略的执行。企业战略的执行一般包括建立组织、配置资源、制定政策、实施领导,以及创造企业文化等。
(3)战略评估:战略监控是企业战略管理过程中的最后一个环节,其基本目的是要保证企业完成规定的战略计划。在监控过程中,一般是将实际执行情况与预期结果进行比较,通过必要的信息反馈正确地评估战略的实施成果,或采取相应的修正措施。实施评估是战略监控的重要内容,必须按照预定的标准和时间进行评价。