摘要:对于【信息系统项目管理师】软考考试而言,试题无疑是最重要的学习资料之一。在软考备考过程中,吃透所考知识点、熟悉出题思路,对我们提升分数的效果是最明显的,通过试题反复练习,还可以查漏补缺。今天,给大家带来【信息系统项目管理师】部分试题的详解,一起来看看吧~



1、estimating schedule activity costs involves developing an () of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives.for example,in mostapplication areas,additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product oprations.the cost estimating process considers whether the expected savings can offset the cost of the additional design work.cost estmates are generally expressed in units of () to facilitate comparisons both within and across projects.the (请作答此空) describes important information about prject requirement that is considered duing cost estimating.
A、 project scope statement
B、 statement of work
C、 project management plan
D、 project policy

答案:A
答题解析:

估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本,成本估算包括设别和考虑各种成本计算方案。例如:在多数的应用领域,普遍在设计阶段多做些额外工作以降低在执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般是以货币单位表示,以利于在项目内和项目间进行比较,项目范围说明书描述了项目的商业要求、理由、需求和当前边界,它提供了关于在成本估算时必须考虑的项目需求的重要信息。



2、需求变更提出来之后,接着应该进行下列中的()
A、 实施变更
B、 验证变更
C、 评估变更
D、 取消变更

答案:C
答题解析:提出变更、评估变更、变更决策、变更实施、变更验证、沟通存档。

3、下列关于项目组合管理的叙述, () 是不恰当的。
A、 项目组合管理借鉴了金融投资行业的投资组合理论
B、 项目组合管理主要是平衡项目的风险和收益,选择最佳的投资组合
C、 组织应该持续地评价和跟踪项目组合的风险和收益情况
D、 项目组合管理是把项目合并起来进行管理

答案:D
答题解析:项目组合管理是一个保证组织内所有的项目都经过风险和收益分析、平衡的方法论,项目组合管理借鉴了金融投资领域的组合管理方法,因此,项目组合管理有时也叫做项目投资组合管理,其基本过程是项目选择和优先级排序,实际上项目组合管理着重于在潜在项目中选择对组织最有利的项目进行实施并平衡资源,而绝不是简单地将项目合并起来进行管理。

查看完整试题>>>