1、A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next?项目经理怀疑最近生产的一批产品存在质量缺陷,对这种缺陷的测试将对产品造成破坏。公司接下来要做什么?
A、 Execute a design of experiments on the batch of products. 在批产品上进行实验设计。

B、 Randomly select units from the batch to measure the extent of the defect. 随机从批中选择单元来测量缺陷的程度。

C、 Execute statistical sampling with pre-defined acceptance criteria. 按照预先定义的验收标准执行统计抽样。

D、 Release the current batch to sell at a discounted price. 释放当前批次以折扣价出售


答案:C
答题解析:

答案C。怀疑存在质量缺陷,对缺陷执行测试又具有破坏性,那就从产品中选出一些样品来进行测试。




2、A project team must develop new technology for a project which has no previous data available. The project manager wants to determine the cost of developing and prototyping this new technology. What should the project manager use to estimate the project' s costs?项目团队必须为没有可用历史数据的项目开发新技术。项目经理想确定开发和原型化这项新技术的成本。项目经理应该用什么来估算项目的成本?
A、 Expert judgment
专家判断
B、 Bottom-up
自下而上

C、 Three point
三点估算
D、 Analogous
类似估算

答案:B
答题解析:

答案B。没有可用历史数据,需要采用自下而上进行累加来进行计算。



3、你是Fun Days Vacation Resorts的项目经理。你的新项目任务是领导在德克萨斯州奥斯汀的Fun Days度假村的开幕。首先,你估计项目管理计划活动的持续时间。当该活动完成后,你开始设计项目进度表,一旦工作开始,你将遵循监测和控制进度表偏差的相关流程。关于这个问题,以下哪项是正确的?选两项
A、这描述了项目整合管理知识领域。
B、这描述了一个预测性的项目管理方法。
C、这描述了项目范围管理知识领域。
D、这描述了项目进度管理知识领域。
E、这描述了一个敏捷的项目管理方法。

答案:B D
答题解析:这描述了项目进度管理知识领域,它涉及以下过程。计划进度管理,定义活动,安排活动顺序,估计活动时间,制定进度表,以及控制进度表。该问题还描述了一种预测性方法。该问题描述了一种循序渐进的方法,即在创建时间表之前完成第一个活动(估算)。在敏捷中,这些活动是一起进行的。