1、A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next?项目经理怀疑最近生产的一批产品存在质量缺陷,对这种缺陷的测试将对产品造成破坏。公司接下来要做什么?
A、 Execute a design of experiments on the batch of products. 在批产品上进行实验设计。

B、 Randomly select units from the batch to measure the extent of the defect. 随机从批中选择单元来测量缺陷的程度。

C、 Execute statistical sampling with pre-defined acceptance criteria. 按照预先定义的验收标准执行统计抽样。

D、 Release the current batch to sell at a discounted price. 释放当前批次以折扣价出售


答案:C
答题解析:

答案C。怀疑存在质量缺陷,对缺陷执行测试又具有破坏性,那就从产品中选出一些样品来进行测试。




2、A project team must develop new technology for a project which has no previous data available. The project manager wants to determine the cost of developing and prototyping this new technology. What should the project manager use to estimate the project' s costs?项目团队必须为没有可用历史数据的项目开发新技术。项目经理想确定开发和原型化这项新技术的成本。项目经理应该用什么来估算项目的成本?
A、 Expert judgment
专家判断
B、 Bottom-up
自下而上

C、 Three point
三点估算
D、 Analogous
类似估算

答案:B
答题解析:

答案B。没有可用历史数据,需要采用自下而上进行累加来进行计算。



3、你是项目经理,你的部门经理来找你,要你帮助他投标新的项目。你想保护你的公司免受金融风险,你的范围定义很有限。最好选择哪种合同?
A、固定总价合同(FFP)
B、总价加经济价格调整合同(FP-EPA)
C、工料合同(T&M)
D、成本加固定费用(CPFF)

答案:D
答题解析:

根据题干描述,“我”是乙方人员,在加上项目的“范围定义有限”,所以不能采用总价合同,因此排除A、B。

工料合同不适合本题意,因此排除C。

站在乙方的角度上,为了保障乙方的利益,最好由甲方报销一切成本,并提供利润,因此选D。