1、If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and( ) of the project management plan. Are revised and reissued to reflect the approved changes
A、 developing baselines
B、 testing baselines
C、 schedule baselines
D、 ending baselines
答案:C
答题解析:暂无
2、In an Information system. The( ) is the bridge between hardware and people
A、 keyboard
B、 internet
C、 disk
D、 data
答案:A
答题解析:暂无
3、Cloud-computing providers offer their “services” according to different models, which happen to form a stack( ), platform as a service (Paas), software as a service (SaaS)
A、 hardware as a service (Haas)
B、 network as a service (NaaS)
C、 infrastructure as a service (IaaS)
D、 data as a service (DaaS)
答案:C
答题解析:暂无