1、If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and( ) of the project management plan. Are revised and reissued to reflect the approved changes
A、 developing baselines
B、 testing baselines
C、 schedule baselines
D、 ending baselines
答案:C
答题解析:暂无
2、有一种游戏为掷两颗骰子,其规则为;当点数和为2时,游戏者输9元;点数和为7或者11时,游戏者赢X元;其他点数时均输1元。依据EMV准侧,当X超过( )元时游戏才对游戏者有利
A、 3.5
B、 4
C、 4.5
D、 5
答案:C
答题解析:暂无
3、In an Information system. The( ) is the bridge between hardware and people
A、 keyboard
B、 internet
C、 disk
D、 data
答案:A
答题解析:暂无