1、 (73) are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated equitably over multiple projects by some approved and documented accounting procedure.
A、 Direct costs
B、 Operation costs
C、 Indirect costs
D、 Implement costs
答案:C
答题解析:
(73) 是指不能直接追溯到特定项目的成本,因此将通过一些批准和记录的会计程序在多个项目上平均累计和分配。
(73)A.直接成本B.运营成本 C.间接成本D.实施成本
2、 Software engineering is the study and application of engineering to the (74) , development and maintenance of software.
A、 research
B、 management
C、 assembly
D、 design
答案:D
答题解析:
软件工程是将工程的研究和应用运用于软件的(74)、开发和维护。
(74)A.研究B.管理 C.集成 D.设计
3、 The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the (75).
A、 Chang control board
B、 Project management office
C、 Project manager
D、 Configuration management officer
答案:C
答题解析:
实施整体变更控制过程是从项目开始到项目结束并且是(75)项目经理的最终责任。
(75)A.变更控制委员会 B.项目管理办公室 C.项目经理 D.配置管理员