摘要:如果你决定参加PMP考试,为了快速通过考试拿到证书,我的建议是一定要重视刷题。PMBOK第六版官方教材900页,埋没在教材中真的会失去方向。多做模拟题、大量地刷题、形成PMP思维很重要,这样当你看题目时,不仅仅看答案的表面现象,更多会透过实质看本质,将思维与PMBOK同步,你就会很轻易做出答案。



1、A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next?项目经理怀疑最近生产的一批产品存在质量缺陷,对这种缺陷的测试将对产品造成破坏。公司接下来要做什么?
A、 Execute a design of experiments on the batch of products. 在批产品上进行实验设计。

B、 Randomly select units from the batch to measure the extent of the defect. 随机从批中选择单元来测量缺陷的程度。

C、 Execute statistical sampling with pre-defined acceptance criteria. 按照预先定义的验收标准执行统计抽样。

D、 Release the current batch to sell at a discounted price. 释放当前批次以折扣价出售


答案:C
答题解析:

答案C。怀疑存在质量缺陷,对缺陷执行测试又具有破坏性,那就从产品中选出一些样品来进行测试。




2、A project team must develop new technology for a project which has no previous data available. The project manager wants to determine the cost of developing and prototyping this new technology. What should the project manager use to estimate the project' s costs?项目团队必须为没有可用历史数据的项目开发新技术。项目经理想确定开发和原型化这项新技术的成本。项目经理应该用什么来估算项目的成本?
A、 Expert judgment
专家判断
B、 Bottom-up
自下而上

C、 Three point
三点估算
D、 Analogous
类似估算

答案:B
答题解析:

答案B。没有可用历史数据,需要采用自下而上进行累加来进行计算。



3、在敏捷项目中,在整个项目中确定和吸引业务相关方,并确保团队了解相关方的业务需求非常重要。哪种选项能支持这种思路?
A、应创建产品待办事项列表,列出所有项目相关方的项目需求。
B、应创建一份敏捷宣言,记录项目相关方,其预期成果和已确定的风险。
C、应在整个项目生命周期内制订和审查项目章程,以确保准确记录相关方的利益和期望。
D、应为所有关键相关方创建一个用户故事,判处他们各自的业务目标和需求。

答案:A
答题解析:

选项A:相关方的需求,需要记录在产品待办事项列表中,并进行排序。所以A是最优选项。

选项B:敏捷宣言不记录相关方、成果、风险。

选项C:项目章程是总体和概况的愿景。

选项D:只创建一个用户故事可能不够。



查看完整试题>>>