1、A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next?项目经理怀疑最近生产的一批产品存在质量缺陷,对这种缺陷的测试将对产品造成破坏。公司接下来要做什么?
A、 Execute a design of experiments on the batch of products. 在批产品上进行实验设计。
B、 Randomly select units from the batch to measure the extent of the defect. 随机从批中选择单元来测量缺陷的程度。
C、 Execute statistical sampling with pre-defined acceptance criteria. 按照预先定义的验收标准执行统计抽样。
D、 Release the current batch to sell at a discounted price. 释放当前批次以折扣价出售
答案:C
答题解析:
答案C。怀疑存在质量缺陷,对缺陷执行测试又具有破坏性,那就从产品中选出一些样品来进行测试。
2、A project team must develop new technology for a project which has no previous data available. The project manager wants to determine the cost of developing and prototyping this new technology. What should the project manager use to estimate the project' s costs?项目团队必须为没有可用历史数据的项目开发新技术。项目经理想确定开发和原型化这项新技术的成本。项目经理应该用什么来估算项目的成本?
A、 Expert judgment
专家判断
B、 Bottom-up
自下而上
C、 Three point
三点估算
D、 Analogous
类似估算
答案:B
答题解析:
答案B。没有可用历史数据,需要采用自下而上进行累加来进行计算。
3、根据观察到的风险触发因素,团队成员判断一个已识别的风险即将发生。风险登记册中已经对该风险规定了应对计划。下一步应该怎么做?()
A、将该风险记录在观察清单中
B、举行团队会议,看能否提出更好的应对方案
C、如果该风险在关键路径上,则应立即采取措施
D、采用管理储备,执行既定的应对计划
答案:B
答题解析:
A.该风险已经在风险登记册中,而且不属于只需加以观察的低优先级风险。
B.正确答案。虽然已经有了应对计划,但风险实际情况不一定与之前预测的完全相同,也许要修改风险应对措施,应该听取团队专家的意见。
C.既然是风险,就一定会影响到项目目标,是否立即采取措施与是否在关键路径上没有必然的联系。
D.对巳经识别的风险,不能用管理储备开支。
考点:实施风险应对过程的工具,专家判断。在确认或修改(如必要)风险应对措施,以及决定如何以最有效率和最有效果的方式加以实施时,应征求具备相应专业知识的个人或小组的意见。
王安点评:集思广益。