1、A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next?项目经理怀疑最近生产的一批产品存在质量缺陷,对这种缺陷的测试将对产品造成破坏。公司接下来要做什么?
答案:C
答题解析:
答案C。怀疑存在质量缺陷,对缺陷执行测试又具有破坏性,那就从产品中选出一些样品来进行测试。
2、A project team must develop new technology for a project which has no previous data available. The project manager wants to determine the cost of developing and prototyping this new technology. What should the project manager use to estimate the project' s costs?项目团队必须为没有可用历史数据的项目开发新技术。项目经理想确定开发和原型化这项新技术的成本。项目经理应该用什么来估算项目的成本?
答案:B
答题解析:
答案B。没有可用历史数据,需要采用自下而上进行累加来进行计算。
3、An approved project change will require dedicated resources from an IT department. The resource’s manager is unavailable to provide approval, but the resource is needed immediately to ensure that the project stays on schedule. What should the project manager do?A. Assign the new work to existing team members.B. Seek guidance from the project sponsor.C. Tell the resource to start working and get approval when the manager is available.D. Refer to the change management plan.一项批准的项目变更将需要一名 IT 部门的专用资源。该资源的经理没有空提供批准,但马上需要该资源以确保项目保持进度。项目经理应该怎么做?
答案:D
答题解析:
参考答案D 。排除 ABC:A 与 C 都是直接让该资源去做事,错;B 寻求发起人的做法不是第一优选项。