摘要:如果你决定参加PMP考试,为了快速通过考试拿到证书,我的建议是一定要重视刷题。PMBOK第六版官方教材900页,埋没在教材中真的会失去方向。多做模拟题、大量地刷题、形成PMP思维很重要,这样当你看题目时,不仅仅看答案的表面现象,更多会透过实质看本质,将思维与PMBOK同步,你就会很轻易做出答案。



1、A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next?项目经理怀疑最近生产的一批产品存在质量缺陷,对这种缺陷的测试将对产品造成破坏。公司接下来要做什么?
A、 Execute a design of experiments on the batch of products. 在批产品上进行实验设计。

B、 Randomly select units from the batch to measure the extent of the defect. 随机从批中选择单元来测量缺陷的程度。

C、 Execute statistical sampling with pre-defined acceptance criteria. 按照预先定义的验收标准执行统计抽样。

D、 Release the current batch to sell at a discounted price. 释放当前批次以折扣价出售


答案:C
答题解析:

答案C。怀疑存在质量缺陷,对缺陷执行测试又具有破坏性,那就从产品中选出一些样品来进行测试。




2、A project team must develop new technology for a project which has no previous data available. The project manager wants to determine the cost of developing and prototyping this new technology. What should the project manager use to estimate the project' s costs?项目团队必须为没有可用历史数据的项目开发新技术。项目经理想确定开发和原型化这项新技术的成本。项目经理应该用什么来估算项目的成本?
A、 Expert judgment
专家判断
B、 Bottom-up
自下而上

C、 Three point
三点估算
D、 Analogous
类似估算

答案:B
答题解析:

答案B。没有可用历史数据,需要采用自下而上进行累加来进行计算。



3、公司收到一家供应商在两年前完成的项目发票,若要避免这个问题,项目经理事先应该做什么?
A、 遵循实施采购过程
B、 遵循结束项目或阶段过程
C、 遵循控制采购过程
D、 遵循控制成本过程

答案:C
答题解析:

C

解析:控制采购是管理采购关系,监督合同绩效,实施必要的变更和纠偏,以及关闭合同的过程。其中,关闭合同要确保已按时按质按技术要求交付全部可交付成果,没有未决索赔或发票,全部最终款项已经付清。 ,



查看完整试题>>>