1、Define Activities is the process of identifying the specific actions to be performed to produce the ( ).

A.project elements      

B. work drafts

C. work package           

D. project deliverables

定义活动是标识要执行的特定操作以生成()的过程。

A、 项目要素

B、 工作底稿

C、 工作包

D、 项目交付物

参考答案:D

2、Project work packages are typically decomposed into smaller componentscalled activities to provide a basis for ( ), scheduling, executing, and monitoring and controlling the project work.

A. reviewing     

B.estimating    

C. auditing    

D. expecting

解析:

项目工作包通常被分解成更小的组件级活动,为()、调度、执行、监视和控制项目工作提供基础。

A、 审查

B、 估计

C、 审计

D、 期待

参考答案:B