摘要:如果你决定参加PMP考试,为了快速通过考试拿到证书,我的建议是一定要重视刷题。PMBOK第六版官方教材900页,埋没在教材中真的会失去方向。多做模拟题、大量地刷题、形成PMP思维很重要,这样当你看题目时,不仅仅看答案的表面现象,更多会透过实质看本质,将思维与PMBOK同步,你就会很轻易做出答案。



1、A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next?项目经理怀疑最近生产的一批产品存在质量缺陷,对这种缺陷的测试将对产品造成破坏。公司接下来要做什么?
A、 Execute a design of experiments on the batch of products. 在批产品上进行实验设计。

B、 Randomly select units from the batch to measure the extent of the defect. 随机从批中选择单元来测量缺陷的程度。

C、 Execute statistical sampling with pre-defined acceptance criteria. 按照预先定义的验收标准执行统计抽样。

D、 Release the current batch to sell at a discounted price. 释放当前批次以折扣价出售


答案:C
答题解析:

答案C。怀疑存在质量缺陷,对缺陷执行测试又具有破坏性,那就从产品中选出一些样品来进行测试。




2、A project team must develop new technology for a project which has no previous data available. The project manager wants to determine the cost of developing and prototyping this new technology. What should the project manager use to estimate the project' s costs?项目团队必须为没有可用历史数据的项目开发新技术。项目经理想确定开发和原型化这项新技术的成本。项目经理应该用什么来估算项目的成本?
A、 Expert judgment
专家判断
B、 Bottom-up
自下而上

C、 Three point
三点估算
D、 Analogous
类似估算

答案:B
答题解析:

答案B。没有可用历史数据,需要采用自下而上进行累加来进行计算。



3、项目团队成员对复杂项目决策所需的时间表示沮丧,审批需要在公司的多个级别上进行。团队领导应该做些什么来提高决策质量?
A、减少所需审批数量,并将决策控制界面扩展到Scrum主管。
B、通过小组决策过程,在组织的所有成员之间建立协作式行为。
C、确保尽快将所有决策传达给项目发起人,并公开发布参与规划。
D、确保项目负责人完全融入到项目团队中,以便他们能够随时制定快速决策。

答案:B
答题解析:

选项A:减少审批环节,减少审批人,敏捷教练没有组织级别的权限。

选项B:审批不仅要经过项目组内部,还需要组织层面,那么必须要要建立协作模式,促进和改善决策流程。所以B为最优选项。

选项C:发起人并不能帮助改善决策。

选项D:只提到了改善项目组内部决策,没有改善组织层面的决策。



查看完整试题>>>